We also took delivery of a vast weight of plasterboard, skilfully craned onto one of the concrete pads that will take part of the mass of the stairway. All is safely gathered in to the dry building.
Stair builders John and Shane paid a final measure-up visit this morning to see how long the staircase supporting legs needed to be. The staircase and platforms have already been built. Handrails still to complete, then off to the galvanisers on Friday with a view to fitting next week.