Cladding - the Final Batch

 The external cladding of Terminal 2 has been the most tedious and difficult part of the whole job but we re almost there.

Phase 1 was to set in place the perfectly good panels that had been removed from Terminal 1.

That revealed obvious and easily measurable gaps for which new panels were made and fitted - Phase 2.  That left some of the trickier gaps still be be made and filled with new panels.  We decided to do the remainder in two batches - Phase 3, missing parapet panels, including parapet internal and external corners.

Phase 4 would be measuring and making the final batch of panels - the walls below the parapets, which account for 17 separate panels.  Specifying and labelling the panels' locations on such a complicated near-finished jigsaw called for initiative and white paint this morning.  Happily yesterday's Storm Alex had left us in glorious sunshine: