Search This Blog

Sunday, 24 July 2011

Walls completed

Tom the joiner has worked hard all weekend and all of the remaining internal walls are now there.   Les Hobson's plumbers start with their first fixing work tomorrow - hopefully so too Mounsey's electricians and ADM Systems' ventilation fitter.

Essentially, the building work has now gone as far as it can until wires and pipes are fitted.

We must wait until 12th August for planning and Listed Building approvals (or not) for the details of the roof room and the retaining walls.

Architect Stuart Green has visited twice during the weekend.

During the coming week we expect to see the annex stairway and roof completed.  

Thanks to amazingly quick and meticulous building work we are at the stage of 'lift-off' for a completed project if other suppliers and contractors can deliver.

No comments:

Post a Comment

Do please leave comments. If nothing else it shows that there is somebody out there.